Paving will begin on May 15th. Below is the tentative schedule, subject to weather or unforeseen circumstances.
The tentative plans are:
Monday afternoon, 5/15: Move in and prep work on some of the streets that are not being milled (primarily Baltimore and W.Baltimore)
Tuesday, 5/16: Milling of Marx, 5th, 9th, 10th, Alley from Sunny to 10th (NO PARKING on those streets when they are there — they are starting on Marx at 7:00 AM and will work their way south)
Wednesday, 5/17: Paving – Marx / Baltimore / W. Baltimore (maybe North Park and parking areas) (NO PARKING from 7:00 to 5:00)
Thursday 5/18: Paving – 5th / 9th/ 10th / Sunny / Alley (NO PARKING from 7:00 to 5:00)
Friday 5/19: Carry-over day
Please note – when they are paving or milling on the east side of Marx/5th/9th/Sunny/10th — they may extend into the first lane of traffic southbound on Wheeling Ave — please proceed with caution.