Street paving will begin next week. The following schedule is tentative, and is subject to change due to weather or other unforeseen circumstances. When the streets are designated for milling, we ask for no parking on those streets until the milling is complete. After it is milled, parking is permitted.
On Monday, July 14th, they plan to mill:
-Railroad St
-Third St from Wheeling Ave to previous paving
-Fifth Street (Tomlinson to Baltimore)
-Fifth Street (Wheeling to Washington)
-Alley between 7th and 8th from Wheeling Ave to Baltimore- if possible
On Tuesday, July 15th, they plan to mill:
-Alley between 7th and 8th if not completed Monday
-Eighth Street from Wheeling Ave to Tomlinson
-Alley between Lee St and 12th
-End of 12th by Baltimore
-Willow Ln from Glen Haven to Lindy
Paving is planned to begin on Wednesday with Railroad St and 3rd St. We will post the schedule when available.